Now that #4683 is done, how do we proceed here?

Can we agree on a schedule containing substeps and dates to turn this huge single block of work into bite-sized pieces?

It might also be useful to identify pieces that can be done by a Tor person with little clue of simulating things or by a simulation person with little clue of writing Tor patches.

I assume November is still the deadline we aim for and that July is unrealistic. Please correct me if that's not the case.

Legend:

Unmodified
Added
Removed
Modified
  • Ticket #4684 – Description

    initial v1  
    1 [wiki:org/sponsors/SponsorF/Year1 Sponsor F deliverable 22] is about implementing one or more [http://www.cl.cam.ac.uk/~sjm217/volatile/datagram-comparison.pdf datagram-based designs] and experimenting with them based on the mid-March testing plan.  We'll discuss the details once deliverable 3 (#4683) is done.  Steven says he's going to lead this deliverable.
     1[wiki:org/sponsors/SponsorF/Year2 Sponsor F deliverable 22] is about implementing one or more [http://www.cl.cam.ac.uk/~sjm217/volatile/datagram-comparison.pdf datagram-based designs] and experimenting with them based on the mid-March testing plan.  We'll discuss the details once deliverable 3 (#4683) is done.  Steven says he's going to lead this deliverable.